2017 Water Main & Road Construction

Construction Update for June 25, 2017 to June 30, 2017


JEFFERSON STREET RESIDENTS:

June 22nd – 23rd:  Concrete Crews will be replacing sidewalks and driveway approaches on Jefferson.

June 23rd – 25th:   Final grading of the gravel on Jefferson and Grove will be completed over the next couple of days.

June 23rd :      Jefferson and Grove will have asphalt installed over the next week.


 WE ASK RESIDENTS TO AVOID THE AREA AND LIMIT DRIVING ON THE NEW ASPHALT FOR THE FIRST DAY    


FULTON AND COLFAX STREET RESIDENTS:

June 23rd:              Streets will be pulverized tomorrow.

June 26th:              Hoffman construction will begin to install the new water main on Fulton and Colfax starting Monday.


PLEASE DO NOT PARK ON JEFFERSON / GROVE / MAIN / FULTON / COLFAX STREETS AT ANY TIME UNTIL FURTHER NOTICE.


The Village of Quincy appreciates your understanding and patience during the construction process.

If you have any questions, please contact the Village Office at

517-639-9065.